LIVEParliament Budget Session 2026: 9 Bills passed — opposition walks out over electoral roll deletions·BREAKINGSupreme Court gives SBI 4 weeks to submit full electoral bond matching data — 22,217 bonds still unlinked·UPDATEDelhi AQI hits Severe for 12 straight days — AIIMS study confirms 34% surge in respiratory emergencies·NEWBudget 2026: ₹11.1 lakh crore for infrastructure — roads got 38%, housing just 9%·UPDATEPM-KISAN: 3.2 crore eligible farmers excluded — land records and Aadhaar seeding failures blamed·NEWAyushman Bharat: 55.4 crore cards issued, only 15.2% ever used — rejection rate 26% nationally·LIVENREGA wages delayed 47+ days across 9 states — 2.4 crore workers unpaid despite completing work·BREAKINGBy-elections 2026: INDIA bloc wins 11 of 14 seats — a warning signal ahead of 2027 state polls·LIVEParliament Budget Session 2026: 9 Bills passed — opposition walks out over electoral roll deletions·BREAKINGSupreme Court gives SBI 4 weeks to submit full electoral bond matching data — 22,217 bonds still unlinked·UPDATEDelhi AQI hits Severe for 12 straight days — AIIMS study confirms 34% surge in respiratory emergencies·NEWBudget 2026: ₹11.1 lakh crore for infrastructure — roads got 38%, housing just 9%·UPDATEPM-KISAN: 3.2 crore eligible farmers excluded — land records and Aadhaar seeding failures blamed·NEWAyushman Bharat: 55.4 crore cards issued, only 15.2% ever used — rejection rate 26% nationally·LIVENREGA wages delayed 47+ days across 9 states — 2.4 crore workers unpaid despite completing work·BREAKINGBy-elections 2026: INDIA bloc wins 11 of 14 seats — a warning signal ahead of 2027 state polls·
NT
🏠 Housing
Overdue

Ministry of Housing & Urban Affairs

Deliver 1 crore completed and occupied houses under PMAY-U by March 2026

PMAY-Urban's FY26 delivery target was set at 1 crore fully completed and occupied housing units for economically weaker sections and low income groups in urban areas.

18percent

Overall Progress

Ministry

Ministry of Housing & Urban Affairs

Budget

₹2.03 lakh crore (cumulative PMAY-U)

Deadline

March 31, 2026

Progress Snapshot

18.4 lakh units completed & occupied of 1 crore target

18%

Last updated: Apr 25, 2026 · Source: MoHUA Dashboard

Milestones

50 lakh grounded

Target: Mar 2025

51.2L ✓

75 lakh completed

Target: Dec 2025

62L — missed

1 crore occupied

Target: Mar 2026

18.4L — missed

Revised target unclear

Target: TBD

Pending

Update Log

Negative

Apr 25, 2026

NHB audit confirms: only 18.4 lakh units fully completed and occupied. MoHUA's 1-crore claim counts in-progress units.

Negative

Mar 31, 2026

Deadline passed. Ministry says 1 crore figure refers to 'grounded and completed' under a broader definition used since 2022.

Negative

Feb 10, 2026

CAG flags 58 lakh sanctioned units past their expected completion date — calls for revised timeline from states.

Negative

Jan 8, 2026

Ministry revises Q4 target from 20 lakh to 14 lakh completions citing material cost escalation and contractor issues.

How we track this

We track only fully completed and occupied units — not those 'sanctioned', 'under construction', or 'grounded'. Our source is NHB's independent audit supplemented by state-level CAG reports. We reject MoHUA's own count which conflates sanctioned + in-progress + completed.

Primary source: MoHUA Dashboard, NHB Audit Report Apr 2026, CAG Performance Audit PMAY-U