Ministry of Housing & Urban Affairs
Deliver 1 crore completed and occupied houses under PMAY-U by March 2026
PMAY-Urban's FY26 delivery target was set at 1 crore fully completed and occupied housing units for economically weaker sections and low income groups in urban areas.
Overall Progress
Ministry of Housing & Urban Affairs
₹2.03 lakh crore (cumulative PMAY-U)
March 31, 2026
Progress Snapshot
18.4 lakh units completed & occupied of 1 crore target
18%Last updated: Apr 25, 2026 · Source: MoHUA Dashboard
Milestones
50 lakh grounded
Target: Mar 2025
51.2L ✓
75 lakh completed
Target: Dec 2025
62L — missed
1 crore occupied
Target: Mar 2026
18.4L — missed
Revised target unclear
Target: TBD
Pending
Update Log
Apr 25, 2026
NHB audit confirms: only 18.4 lakh units fully completed and occupied. MoHUA's 1-crore claim counts in-progress units.
Mar 31, 2026
Deadline passed. Ministry says 1 crore figure refers to 'grounded and completed' under a broader definition used since 2022.
Feb 10, 2026
CAG flags 58 lakh sanctioned units past their expected completion date — calls for revised timeline from states.
Jan 8, 2026
Ministry revises Q4 target from 20 lakh to 14 lakh completions citing material cost escalation and contractor issues.
How we track this
We track only fully completed and occupied units — not those 'sanctioned', 'under construction', or 'grounded'. Our source is NHB's independent audit supplemented by state-level CAG reports. We reject MoHUA's own count which conflates sanctioned + in-progress + completed.