LIVEParliament Budget Session 2026: 9 Bills passed — opposition walks out over electoral roll deletions·BREAKINGSupreme Court gives SBI 4 weeks to submit full electoral bond matching data — 22,217 bonds still unlinked·UPDATEDelhi AQI hits Severe for 12 straight days — AIIMS study confirms 34% surge in respiratory emergencies·NEWBudget 2026: ₹11.1 lakh crore for infrastructure — roads got 38%, housing just 9%·UPDATEPM-KISAN: 3.2 crore eligible farmers excluded — land records and Aadhaar seeding failures blamed·NEWAyushman Bharat: 55.4 crore cards issued, only 15.2% ever used — rejection rate 26% nationally·LIVENREGA wages delayed 47+ days across 9 states — 2.4 crore workers unpaid despite completing work·BREAKINGBy-elections 2026: INDIA bloc wins 11 of 14 seats — a warning signal ahead of 2027 state polls·LIVEParliament Budget Session 2026: 9 Bills passed — opposition walks out over electoral roll deletions·BREAKINGSupreme Court gives SBI 4 weeks to submit full electoral bond matching data — 22,217 bonds still unlinked·UPDATEDelhi AQI hits Severe for 12 straight days — AIIMS study confirms 34% surge in respiratory emergencies·NEWBudget 2026: ₹11.1 lakh crore for infrastructure — roads got 38%, housing just 9%·UPDATEPM-KISAN: 3.2 crore eligible farmers excluded — land records and Aadhaar seeding failures blamed·NEWAyushman Bharat: 55.4 crore cards issued, only 15.2% ever used — rejection rate 26% nationally·LIVENREGA wages delayed 47+ days across 9 states — 2.4 crore workers unpaid despite completing work·BREAKINGBy-elections 2026: INDIA bloc wins 11 of 14 seats — a warning signal ahead of 2027 state polls·
NT
💧 Infrastructure
At Risk

Ministry of Jal Shakti

Provide functional tap water connections to all 19.19 crore rural households by 2024

Launched in 2019, JJM aimed to connect every rural household with piped drinking water. The target deadline of 2024 was missed; revised deadline is now December 2026.

79percent

Overall Progress

Ministry

Ministry of Jal Shakti

Budget

₹3.60 lakh crore (revised total)

Deadline

December 31, 2026 (revised from 2024)

Progress Snapshot

15.16 crore connections (79%) of 19.19 crore target

79%

Last updated: Apr 10, 2026 · Source: JJM Official Dashboard

Milestones

50% households covered

Target: Mar 2022

Achieved ✓

Original 100% target

Target: Dec 2024

79% — missed

90% coverage

Target: Jun 2026

On trajectory

Revised 100% target

Target: Dec 2026

At risk

Update Log

Negative

Apr 10, 2026

JJM dashboard: 15.16 crore connections. NITI evaluation finds 28% non-functional — effective functional coverage is ~11 crore HH.

Negative

Mar 5, 2026

19,412 villages still without any connection — mostly in hilly/tribal regions. Ministry says these are 'technically challenging terrains'.

Negative

Feb 20, 2026

Water quality data unavailable for 31% of covered habitations — ministry directed to submit state-wise quality testing reports.

Positive

Jan 25, 2026

Jal Jeevan Mission celebrated 75% milestone — PM Modi addresses virtual event from New Delhi.

How we track this

We track JJM's own dashboard data but also cross-reference with NITI Aayog's concurrent evaluation, which found 28% of claimed 'functional' connections were non-operational at time of inspection. Our figure uses the dashboard number with a footnote on the functionality gap.

Primary source: JJM Official Dashboard, NITI Aayog Concurrent Evaluation 2025, CAG Performance Audit JJM
#JJM#drinking water#rural#sanitation#Jal Shakti